Yup...transfer switches, etc are going to be VERY important and my current
thought is to utilize the science logic scripting system to force certain
things to happen in a particular order...like wait time for generator to
stabilize instead of instant switch over.
/brian chee
On 11/8/10 1:45 PM, "John Call" <johncall at byuh.edu> wrote:
> Are you factoring in for the auto-transfer switch and electrical contact work
> as well? I'm doing an 80kW presently...
>
> John
>
> Sent from my Samsung Epic™ 4G
>
> Brian Chee <chee at hawaii.edu> wrote:
>
>
> So I¹m looking at exploring the potential for a small (approx 20kw)
> generator to get past long (more than 20 minutes) power outages for critical
> servers. Does anyone have some wisdom they can share with me?
>
> /brian chee
>
> --
> Brian Chee
> University of Hawai'i at Manoa
> School of Ocean and Earth Sciences and Technology (SOEST)
> 2525 Correa Road, HIG 500
> Honolulu, HI 96822
> Tel: 808-956-5797
>
>
> _______________________________________________
> LUAU at lists.freesoftwarehawaii.org mailing list
> http://lists.freesoftwarehawaii.org/listinfo.cgi/luau-freesoftwarehawaii.org
> _______________________________________________
> LUAU at lists.freesoftwarehawaii.org mailing list
> http://lists.freesoftwarehawaii.org/listinfo.cgi/luau-freesoftwarehawaii.org
--
Brian Chee
University of Hawai'i at Manoa
School of Ocean and Earth Sciences and Technology (SOEST)
2525 Correa Road, HIG 500
Honolulu, HI 96822
Tel: 808-956-5797
More information about the LUAU
mailing list